Section 20 consultation software keeps the record a landlord, RMC or RTM company needs to show it consulted leaseholders before charging for major works: which notice went to which flat, when and how, the 30-day observation periods, the estimates and every observation received. Marklet does this for blocks in England.
Section 20 of the Landlord and Tenant Act 1985 and the Service Charges (Consultation Requirements) (England) Regulations 2003, in brief.
Where works will cost any one leaseholder more than £250, the landlord has to consult before the cost can be recovered in full. "Landlord" includes anyone with a right to enforce payment of a service charge, which can include an RMC. Once an RTM company has acquired the right to manage, references to the landlord are to the RTM company.
An agreement for more than 12 months, such as a cleaning, lift or management contract, needs consultation where it will cost any one leaseholder more than £100 in an accounting period.
Each notice that invites observations gives leaseholders 30 days, beginning with the date of the notice, to make them in writing, and the landlord has to have regard to what they say.
If the procedure is not followed and the First-tier Tribunal does not grant dispensation, the landlord can recover no more than £250 from each leaseholder for the works.
Not sure whether a job needs consulting on? Try the free section 20 checker. No sign-up.
One proceeding per consultation, for works, for a long term agreement, or for works under an agreement you already have.
Served on each flat and on any recognised tenants' association, each with the date it was given and how: by post, by hand, or electronically where the leaseholder has agreed to that. Observations, and nominated contractors where the procedure invites them, come back against this stage.
The estimates obtained and the stage 2 notice, served and dated per flat like the first. Observations on the estimates are kept apart from those on the intention.
The notice that follows the contract, where the procedure requires one, recorded in the same way.
Where an application is made to the tribunal to dispense with all or any of the requirements, the application and its outcome are recorded on the same proceeding.
Whether it is Marklet, your managing agent's system or a spreadsheet.
"We posted them" is not a record a tribunal can check. Look for the date and method of service for every leaseholder and for the recognised tenants' association.
A cleaning or lift contract can need consultation just as a roof can, and works carried out under an existing agreement follow a shorter procedure of their own.
An observation that sits in one director's inbox cannot be summarised or answered. It belongs against the stage it responds to, whether it arrived in the app, by email or by post.
The time to find out a job needs consulting on is before the quote is accepted, not when the demand goes out.
Everything else on the Management plan is on the features page. Plans and per-unit prices are on the pricing page.
Software that keeps the record a landlord, RMC or RTM company needs to show it consulted leaseholders before charging for major works or a long term agreement: which notice went to which flat, when and how, the 30-day observation periods, the estimates and the observations received.
In England, consultation is needed to recover more than £250 from any one leaseholder for works, or more than £100 from any one leaseholder in an accounting period under an agreement of more than 12 months. The free section 20 checker works through the tests for a particular job.
Unless the First-tier Tribunal grants dispensation, what the landlord can recover is capped at £250 for each leaseholder for the works, or £100 for each leaseholder in each accounting period for a long term agreement.
Yes. Accepting a contractor's quote checks whether the job crosses the consultation threshold. You can still go ahead, but what was outstanding is recorded.
Section 20 is on the Management plan.
Get started